Maintenance to York DC Network

Expected resolution: 11 Aug 2016, 03:00 UTC
Return to issues
Issue status: Resolved Date:

11 Aug 2016
02:07 UTC

Posted by:

Nat Lasseter

This work is now complete.

If there are any issues please contact support@bytemark.co.uk.

Issue status: Investigating Date:

10 Aug 2016
22:49 UTC

Posted by:

Nat Lasseter

The final night of work is upon us.

This is a reminder that we will be performing the remainder of the network maintenance work as mentioned below.

All affected customers have been emailed.

Work will commence at 0000 (Europe/London).

Thanks

Næþ'n

Issue status: Investigating Date:

10 Aug 2016
02:29 UTC

Posted by:

Nat Lasseter

Good morning

All of the work this morning is now complete without any issues.

The last of the work will be finished tomorrow morning.

Thanks Næþ'n

Issue status: Investigating Date:

9 Aug 2016
21:43 UTC

Posted by:

Nat Lasseter

Good evening

This is a reminder that we will be performing the network maintenance work as mentioned below.

All affected customers have been emailed.

Work will again commence at 0000 (Europe/London).

Thanks Næþ'n

Issue status: Investigating Date:

9 Aug 2016
02:18 UTC

Posted by:

Tom Hill

All of our work has been completed this evening, with only the planned (minimal) impact to single-homed customers as expected.

More switch upgrades are planned for tomorrow night, beginning again at midnight, so we'll be back then.

Tom & Næþ'n

Issue status: Investigating Date:

8 Aug 2016
22:11 UTC

Posted by:

Tom Hill

A timely reminder that our work to upgrade the access switches, will be continuing this evening.

Those customers specifically affected by this evening's switch reloads will already have been emailled.

Work will begin at midnight (in approximately 50 minutes time).

Tom

Issue status: Investigating Date:

26 Jul 2016
13:37 UTC

Posted by:

Nat Lasseter

Hello

The work today was again completed successfully and without incident.

The rest of the work will take place outside of UK working hours on the 9th, 10th, and 11th of August, as it may incur downtime for the attached hosts.

Thanks Næþ'n

Issue status: Investigating Date:

25 Jul 2016
15:27 UTC

Posted by:

Nat Lasseter

Hello

The work today was completed successfully and without incident.

There will be more work happening tomorrow (26th of July) and on the 9th, 10th, and 11th of August.

Næþ'n

Issue status: Investigating Date:

25 Jul 2016
09:34 UTC

Posted by:

Nat Lasseter

Hello

This work will be starting at 1100 (UTC+1) today.

There should be no outages caused by the work, as all machines connected to these devices will have two uplinks to different switches.

Please contact support if you have any issues.

Thanks Næþ'n

Issue status: Investigating Date:

18 Jul 2016
16:57 UTC

Posted by:

Nat Lasseter

We are going to be performing upgrades on all of the switches in the York DC1.YO26 Data Centre.

All affected customers will be emailed, along with times of the affected components.

If you have any questions or concerns regarding this, please contact support.