13 Sep 2016
17:13 UTC
Chris Cottam
All switches are now repatched, everything should be as normal
Issue resolved
13 Sep 2016
12:44 UTC
Tom Hill
Repatching is going well, and a number of switches will now have been returned to full resilience (i.e. with both core switch uplinks present).
This work will continue for a number of hours. If there aren't any surprises, we'll update again when the work is completed.
13 Sep 2016
10:00 UTC
Tom Hill
The core switch is now down and is being relocated. All operations have continued without interruption on the remaining core switch.
Repatching will continue for some hours after this point, and should also be a seamless return to full protection for each downstream switch.
13 Sep 2016
09:02 UTC
Chris Cottam
Work about to begin
We do not anticipate any interruption to service
13 Sep 2016
09:01 UTC
Chris Cottam
Between 10am and 8pm UTC we will reconfiguring and relocating one of the core switches in York.
During this period there will be reduced resiliency but no service interruptions are expected.
Further updates will be added here as maintenance progresses
30 Aug 2016
15:29 UTC
Chris Cottam
Between 10am and 8pm UTC we will reconfiguring and relocating one of the core switches in York.
During this period there will be reduced resiliency but no service interruptions are expected.
Further updates will be added here as maintenance progresses