Core switch relocation, York

Expected resolution: 13 Sep 2016, 19:00 UTC
Return to issues
Issue status: Resolved Date:

13 Sep 2016
17:13 UTC

Posted by:

Chris Cottam

All switches are now repatched, everything should be as normal

Issue resolved

Issue status: Investigating Date:

13 Sep 2016
12:44 UTC

Posted by:

Tom Hill

Repatching is going well, and a number of switches will now have been returned to full resilience (i.e. with both core switch uplinks present).

This work will continue for a number of hours. If there aren't any surprises, we'll update again when the work is completed.

Issue status: Investigating Date:

13 Sep 2016
10:00 UTC

Posted by:

Tom Hill

The core switch is now down and is being relocated. All operations have continued without interruption on the remaining core switch.

Repatching will continue for some hours after this point, and should also be a seamless return to full protection for each downstream switch.

Issue status: Investigating Date:

13 Sep 2016
09:02 UTC

Posted by:

Chris Cottam

Work about to begin

We do not anticipate any interruption to service

Issue status: Investigating Date:

13 Sep 2016
09:01 UTC

Posted by:

Chris Cottam

Between 10am and 8pm UTC we will reconfiguring and relocating one of the core switches in York.

During this period there will be reduced resiliency but no service interruptions are expected.

Further updates will be added here as maintenance progresses

Issue status: Investigating Date:

30 Aug 2016
15:29 UTC

Posted by:

Chris Cottam

Between 10am and 8pm UTC we will reconfiguring and relocating one of the core switches in York.

During this period there will be reduced resiliency but no service interruptions are expected.

Further updates will be added here as maintenance progresses