25 Mar 2020
11:42 UTC
Mark Egan-Fuller
Due to the ongoing situation with COVID-19 this work has now been postponed and will be rescheduled at a later date.
Expected resolution time updated: 25 Mar 2020, 11:30 UTC
26 Mar 2020
23:00 UTC
Mark Egan-Fuller
As part of an ongoing project to upgrade our network we need to replace a number of switches in our Manchester Data Centre.
Whilst our network is built to be redundant and we don't expect any outages, all Manchester based services including Manchester based BigV cloud servers will be considered at risk for the duration of the maintenance.
Staff will be on site and remote monitoring the situation, with additional staff on standby to recover from any potential outages.
Expected resolution time updated: 27 Mar 2020, 07:00 UTC